MTCC contracted to develop roads in Hoarafushi, RDC in Hinnavaru and Thinadhoo

RDC is contracted to develop roads in Lh. Hinnavaru and GDh. Thinadhoo on April 8, 2021. (Photo/Planning Ministry)

Planning Ministry has contracted Maldives Transport and Contracting Company (MTCC) to design and develop asphalt roads in HA. Hoarafushi, and Road Development Corporation (RDC) to design and develop asphalt roads in Lh. Hinnavaru and GDh. Thinadhoo.

Planning Ministry signed the contracts with MTCC and RDC this Thursday morning.

The Hoarafushi road development project is valued at MVR 71.91 million.

MTCC is contracted to complete the project within 470 days.

Under the project, MTCC will cover 5.3 kilometers of road will asphalt, install light fixtures, and establish a drainage system.

MTCC is contracted to develop roads in HA. Hoarafushi on April 8, 2021. (Photo/Planning Ministry)

The Hinnavaru road development project is valued at MVR 122.08 million.

RDC is contracted to complete the project within 540 days.

Under the project, RDC will cover 7.1 kilometers of road will asphalt, install light fixtures, and establish a drainage system.

The Thinadhoo road development project is valued at MVR 78.80 million.

RDC is contracted to complete the project within 450 days.

Under the project, RDC will cover 6.5 kilometers of road will asphalt and install light fixtures.